Foshan container mobile house installation process
2024-01-15

佛山集装箱活动房

1. erection frame

Simply screw the four uprights on the base plate, then put the top plate up and install the drain pipe. Be sure to confirm that the ground is level, and then confirm that the diagonal dimensions are consistent. Adjust the outer edge of the column to be vertical and flush with the top surface and the outer edge of the floor frame before fixing the bottom and top screws.
2. Vertical wall panels
Before installing wall panels, read the drawings carefully and install them according to the codes marked in the drawings. The flat opening of the wall panel should be on the inside, and the inlaid opening should be facing outward. When splicing, use a steel bar to clamp it at the tiger's mouth. Remember not to use too much force to tear the board apart. If there is a large gap in the socket, use rivets to refix it.
3. Vertical partition board
Before installing the partition board, first use rivets to fix the angle aluminum on which the partition board is installed on one side. Install the entire wall panel first, then install the small door side panel and door head board, then install the grooved aluminum at the door frame. Fix the other aluminum corner of the top handle.
4. Install angle aluminum
Cut the corresponding corner aluminum according to the internal dimensions and install it counterclockwise. The top corners are installed first. The corner aluminum at the diagonal corners cannot overlap.
5. Install windows
First install the aluminum window frame. The aluminum window frame requires a 45-degree angle and is fixed on the composite panel with rivets. After the aluminum window frame is installed, install the window, adjust it, and fix it to the aluminum window frame with a self-drilling top;
6. Install door locks and hinges
Put the door into the door frame and fix it with wedge plates around it. The gap must be even. Pay attention to whether the position of the door lock and the lock hole on the door frame are aligned. Install the hinge at one time and fix it to the aluminum door frame with rivets; install the door lock according to the The photo shows the disassembly, first install the outer part and then the inner part, put on the side shield and tighten the door lock.
7. Install lights
Lamp holder specifications: 2X36W Dimensions: 1258X315X318mm. Lamp tube: 36W8T standard fluorescent lamp. Separate the lamp wires with a knife, connect the lamp wires to the lamp stand, and then screw the lamp rack to the wall panel with self-tapping nails. Install the light tube,
Insert the plastic lampshade from one end and install the baffles at both ends.
8.Connect electricity
Separate the wires with a knife and fix them with porcelain heads. Fix the PVC wiring trough on the wall. Fix the socket junction box on the wall panel with self-drilling nails. Install the sockets and switches and fasten the PVC trough; socket The height from the ground is 400mm, and the height of the switch from the ground is 1300mm.
9. Apply sealant
Apply glue and seal around windows and wall composite panels
10.Finished product
Tear off the protective film on the composite panels and doors and windows